Critical Path though Multiple Projects
Forum Sponsor
Top Posters
Nick Johnson-Pond
3 posts
sairedz25
0 posts
Ahmed Awad
2 posts
Syed Shoeb
0 posts
Vimukthi
0 posts
bal aji
2 posts
Lee Mallek
23 posts
Viet Tran
9 posts
Ola Gbotoso
0 posts
Jaturapit Multongka
1 posts
Hi,
I write an article regarding How to display just One Critical path with Multiple projects open in Primavera P6.
If you're interested, kindly read it here https://doduykhuong.wordpress.com/2016/08/29/how-to-display-just-one-critical-path-with-multiple-projects-open-in-primavera-p6/
Hi David
Thats why I use a finish milestone with a constraint "Must Finish By". P5/P6 then will regard those projects as one graph (=project) for calculation and I experienced proper results.
Regards
Dieter
Calculation of float in a multi-project scenario.
Let us assume a two project “portfolio” consisting of a “design” project and a “construction” project.
There are many interrelationships, primarily design->construction.
If neither project has a “must-finish-by” date at the project level, then when we schedule them in P5/6 the late finish of each project is assumed to be the early finish of each project.
Therefore the amount of float in an activity in the design project will be the smallest of the float imposed by its construction successor or the float imposed by its assumed “must finish-by” date.
If I want ONE float/critical path as the unmentionable 16-bit planning package offers under “Project Group Scheduling, Base Float on end of Project Group”
Then we have to set the “Must Finish by” date at the project level to the same date for each project.
This seems to work fine as far as I have tested it.
Hi David
"F9" --> Options --> Advanced
There you can select Multiple Float Paths. But I dont know if it works exactly the same as in P3.
Then you can group by multiple float paths (under "General").
Set all projects to the same data date then it will calculate them as one graph.
For the "must finish by"-date I always use milestones with a mandatory constraint because Im always aware in the activities-view. The entry in the projects view I might forget - due to experience: will...
Regards
Dieter
Set Project CP to Longest Path
and if you now Group & Sort in this order by
Longetst Path
Then
by Project-WBS
you will have multiple projects with single critical path.
Let me know if it works
Sandy