P5 Physical % Complete does not roll up
Forum Sponsor
Top Posters
Nick Johnson-Pond
3 posts
sairedz25
0 posts
Ahmed Awad
2 posts
Syed Shoeb
0 posts
Vimukthi
0 posts
bal aji
2 posts
Lee Mallek
23 posts
Viet Tran
9 posts
Ola Gbotoso
0 posts
Jaturapit Multongka
1 posts
I have tested on my PC and it show curve correctly when tick on checkbox of Earned value curve.
You can show "Planned value cost" on activity table to see whether it have value.
Hi Donovan.
Unfortunately we still have not understood your request.
What window are you currently in to show histogram? Tracking or Activities.
Thanks
Thanks K D ,Really appreciate your help, will try and let you know,I also need to show a histogram with planned, actual & earned and scurves for the same in one profile,
my profile histogram shows my budget,baseline,and actual,but the scurves,I have the planned value labour units & earned value labour units ticked but is not showing,
Please help
Regards
Donovan
Hi buddy.
Physical % complete is not rolled up, because it is a
discrete, user entered value assigned to an activity. Since
Physical % Complete does not relate to the duration,
units or costs of the activity, there is no common
denominator to use for the summary
Workaround:
It is possible to configure the Activitys Performance %
complete to equal the Physical % complete.
Performance % complete can be rolled up to the summary
bands. However, to achieve this, the following three
statements need to be true:
1) The % Complete type of the activities must be
set to Physical % complete.
2) The Technique for calculating performance %
Complete needs to be set to Activity % complete.
3) Finally, in order for the Performance %
Complete to be rolled up to the summary band(s),
costs need to be assigned to the activity. These
costs must also be present in the Primary baseline.
This solution derive from Primavera