Using Primavera SureTrak I can get the reports and filters with ease. Being Suretrak a low end and outdated Primavera product this should be a walk in the park under P6.
http://rapidshare.com/files/251857683/Organize_by_Successor_or_Predeces…
Hope this give you the clue.
Rafael
Hi Suchitra
[email protected]
Regards
Hi Suresh Gurubhavan,
I tried to get in touch with you through planning planet but currently private messaging is restricted on planning planet,can you please share me your email id,i would like to discuss regarding P6 with you
Regards
Suchi
badddddddd
Ooops... Karim
I got kicked off from there... because i am using 3.5.1 version.. I cant export relationship... also i cant export to xls....
Hi Karim
I think its having the logic. I think i will try your method.. Thanks...
Hi Suresh,
OK I now get it but sorry as far as I know there is no automatic way to do it (neither a report nor layout export will do it at one shot).
What I manged to do is:
1- Export the schedule relationships (File - Export - Spreadsheet XLS - Activity Relationships), set a template in which u’ll be showing the predecessors data only (eg. Start / Finish / ID / Status) - sheet #1.
2- Back to your schedule, remove all the columns except Act. ID / Activity Name and add the column named Predecessors.
3- Select the schedule data (press ctrl+A) and then paste it in another excel sheet - sheet #2.
4- Now u have 2 excel files, one contains activities data and the other containing predecessors data, u can use vlookup formula in linkage between the 2 sheets (ie. search for predecessors ID from sheet #2 and gets its info from sheet #1).
Regards,
Karim
Hey
Pls try to understand what i really mean.
I want to show a schedule plan / report which shows the main activity and the predecessor activity status.
Eg:
Act.id Act.name Start Finish Predcessor Predecessor status
00100 Relagging 10/10 12/10
Box-up line In-prgss
This is what i want. I want to see the predecessor activitys status and not the main activity status.
Hey
Pls try to understand what i really mean.
I want to show a schedule plan / report which shows the main activity and the predecessor activity status.
Eg:
Act.id Act.name Start Finish Predcessor pred.status
00100 Relagging 10/10 12/10 Box-up line In-prgss
This is what i want. I want to see the predecessor activitys status and not the main activity status.
Good Question Suresh...
To show the activities which havent started, you can give filter of
Select if Is Low Value High Value
early start WR DD DD + 2W
If u want to know the predecessaors status, then that you have to do it manually
:-)
I think you can only show up the predecessor manually.
In the report "activity relation" filter for the activites which havent started yet.
(ie. percent complete = 0%).