there are sereval way to achieve the start and stop



1. Constraint - Supspend and Resume - when you update the schedule then you can either select what date is supspended or resumed. This is useful if you dont know when the activity is stopped



2. Calendar - you can create a specific calendar for this activity so that you can planned which time period will be non working and which is working. This is useful if you have several known stoppage



3. use combination of 1 and 2



Good Luck