Importing from P3 to P5
Forum Sponsor
Top Posters
Nick Johnson-Pond
3 posts
sairedz25
0 posts
Ahmed Awad
2 posts
Syed Shoeb
0 posts
Vimukthi
0 posts
bal aji
2 posts
Lee Mallek
23 posts
Viet Tran
9 posts
Ola Gbotoso
0 posts
Jaturapit Multongka
1 posts
Hi Dev
There is aparameter in the import procedure. If you select "Combine subproject" the activity codes will be imported as project activity codes. Otherwise as global.
Regards
Dieter