mh shaw 👤 Member for 19 years 1 month
A
Andrew Dick 👤 Member for 19 years 4 months

If they are still there and you can’t work out why.



As I’ve just found out, if you have no requirement for Logic links to external projects, add the columns ’External Early Start’ & ’External Late Finish’, then remove any data in there.



This will then clear the remainder of the "*".



Andy

R
Rodel Marasigan 👤 Member for 19 years 7 months

mh shaw,



On the activity detail select the status tab and remove any constrains and date shown on the constrains box



Hope this help.



Rodel