7.5hr working day?
Forum Sponsor
Top Posters
Nick Johnson-Pond
3 posts
sairedz25
0 posts
Ahmed Awad
2 posts
Syed Shoeb
0 posts
Vimukthi
0 posts
bal aji
2 posts
Lee Mallek
23 posts
Viet Tran
9 posts
Ola Gbotoso
0 posts
Jaturapit Multongka
1 posts
Beck,
Deb is correct. I forgot to mention that you need to set the decimal on duration format. Edit-> Users Preferences... under your project menu.
Select Time Unit Tab and change the duration format to 1 or 2 decimal. If this is not set the calculation still based on 7.5 hours but shown as 8hrs round off. You will notice only on the total durations.
Regards,
Rodel
u have to change in project over view to 2 decimal places , i hope this will solve the rounding problem
regards
deb
Thanks for your reply Rodel..
I had already done that, but I suppose my question is more because when I assign a resource to a 1 day activity, it assigns that resource with 8hrs of work and budget - even though the calendar for that resource is also set as default 7.5hr/day.. I can override this and type in 7.5 in the units column, which gives the right budget, but it still displays 8 (because of rounding?) in the units column.. Is there a way to correct this and show the decimal place in the units field?..
Thanks again!
Beck
Hi Beck,
Yes you can set the calendar for 7.5hrs default for a work day.
First Create a global calendar with 7.5 hrs working day. Then click this calendar or set as default.
Regards,
Rodel