Baseline

H
hamed planner 👤 Member for 19 years 2 months

Marcio ,





at the time you set your currnt project as a Baseline as you mentioned

your planned start = Base line start

Planned Finish = Base line finish which is correct untill your first update of the schedule



also



as you prgress they will change ,



They are couple of good query regarding baseline i suggest ou review them,





Regards,



Hamed

D
David Kelly 👤 Member for 21 years 7 months

Was there any progress in your project when you made the first baseline?

Forum Sponsor

Top Posters

Nick Johnson-Pond
3 posts
sairedz25
0 posts
Ahmed Awad
2 posts
Syed Shoeb
0 posts
Vimukthi
0 posts
bal aji
2 posts
Lee Mallek
23 posts
Viet Tran
9 posts
Ola Gbotoso
0 posts
Jaturapit Multongka
1 posts