Progressing without Updating
Forum Sponsor
Top Posters
Nick Johnson-Pond
3 posts
sairedz25
0 posts
Ahmed Awad
2 posts
Syed Shoeb
0 posts
Vimukthi
0 posts
bal aji
2 posts
Lee Mallek
23 posts
Viet Tran
9 posts
Ola Gbotoso
0 posts
Jaturapit Multongka
1 posts
Mathew,
Run the "update progress" under tools menu, enter the desired date when prompted and then click run.
Hope this helps.
BEN
Hi Mathew,
I think youre referring to Progress Spotlight where you can update your progress against you data date. Any activities highlighted by progress spotlight will be updated automatically without extending dates.
HTH
Rodel
Hi Matthew,
U can use the "Schedule % complete" to show how much of the activitys baseline duration has been completed so far (till the data date).
U can make a copy of the schedule that u work on and assign a baseline to it, then update the schedule as per ur data date and ull find the "Schedule % complete".
HTH.
Regards,
Karim