Progressing without Updating

R
ruben quintal 👤 Member for 19 years 8 months

Mathew,



Run the "update progress" under tools menu, enter the desired date when prompted and then click run.

Hope this helps.



BEN

R
Rodel Marasigan 👤 Member for 19 years 7 months

Hi Mathew,



I think you’re referring to Progress Spotlight where you can update your progress against you data date. Any activities highlighted by progress spotlight will be updated automatically without extending dates.



HTH

Rodel

K
Karim Mounir 👤 Member for 20 years 2 months

Hi Matthew,



U can use the "Schedule % complete" to show how much of the activity’s baseline duration has been completed so far (till the data date).



U can make a copy of the schedule that u work on and assign a baseline to it, then update the schedule as per ur data date and u’ll find the "Schedule % complete".



HTH.



Regards,

Karim

Forum Sponsor

Top Posters

Nick Johnson-Pond
3 posts
sairedz25
0 posts
Ahmed Awad
2 posts
Syed Shoeb
0 posts
Vimukthi
0 posts
bal aji
2 posts
Lee Mallek
23 posts
Viet Tran
9 posts
Ola Gbotoso
0 posts
Jaturapit Multongka
1 posts