Showing Non Work Period in Bar Chart in P3e

N
Nitin Naik 👤 Member for 21 years 4 months
A
Andrew Pearce 👤 Member for 25 years

If you want grahical enhancements like that then you need to buy Powerproject by Asta Developments.



http://www.astadev.com/index.asp



Not got the high power number crunching ability of Primavera but far better graphical output for use in general Construction projects

N
Nitin Naik 👤 Member for 21 years 4 months

Hi,



Thanks Arthur for your reply.



I was mainly after showing a non work period throughtout barchart like you would achieve by using ’curtain’ function.



Thanks once again