Hi Richard,
Simple because P5 storing hrs and not days. Even you change your parameter in user’s preference into day it will not convert hrs to day on calculation. There is a good discussion in this thread (http://www.planningplanet.com/forum/forum_post.asp?fid=1&Cat=8&Top=28096) explained by Ronald Winter.
Regards,
Rodel