Applying Progress to a Level of Effort Activity

J
Jim Fairchild 👤 Member for 23 years 3 months

Check your Project Preferences under the Calculations tab. If you are entering Actual Units manually you need to make sure that the "Recalculate Actual Units and Costs when the duration % changes" is unchecked.

D
Dieter Wambach 👤 Member for 19 years 5 months

Phil,

actual units and level of efforts does work in P3e. There should be a mistake.

Some questions:

- LoE has no fixed duration, because its duration depends from other activities, so either fixed units or fixed untis/time - but this doesn’t produce your situation.

- Did you create correct relationships (SS then FF)?

- Did a resource report actuals as well - via Timesheets?



Sorry, no answer, just more questions



Dieter

Forum Sponsor

Top Posters

Nick Johnson-Pond
3 posts
sairedz25
0 posts
Ahmed Awad
2 posts
Syed Shoeb
0 posts
Vimukthi
0 posts
bal aji
2 posts
Lee Mallek
23 posts
Viet Tran
9 posts
Ola Gbotoso
0 posts
Jaturapit Multongka
1 posts