Applying Progress to a Level of Effort Activity
Forum Sponsor
Top Posters
Nick Johnson-Pond
3 posts
sairedz25
0 posts
Ahmed Awad
2 posts
Syed Shoeb
0 posts
Vimukthi
0 posts
bal aji
2 posts
Lee Mallek
23 posts
Viet Tran
9 posts
Ola Gbotoso
0 posts
Jaturapit Multongka
1 posts
Thanks guys.
Both of your contributions were helpfull in resolving my problem.
Check your Project Preferences under the Calculations tab. If you are entering Actual Units manually you need to make sure that the "Recalculate Actual Units and Costs when the duration % changes" is unchecked.
Phil,
actual units and level of efforts does work in P3e. There should be a mistake.
Some questions:
- LoE has no fixed duration, because its duration depends from other activities, so either fixed units or fixed untis/time - but this doesnt produce your situation.
- Did you create correct relationships (SS then FF)?
- Did a resource report actuals as well - via Timesheets?
Sorry, no answer, just more questions
Dieter