Splitting a P3e Schedule

J
Jaime Linchangco 👤 Member for 24 years 11 months

Hi Emma and Jim,



Good day! Your suggestion works!



What i did was, copy File A to File B. At File B, i deleted all activities. Then open both files. From WBS of File A, i Cut and Paste the the EPCM portion to File B and retain FS portion from File A.



All EPCM activities were moved to File B while maintaining their inter relationships with File A.



Jim suggestions must be followed as well. A "Must Finish By" Date should be assigned from File A (or FS) so that backward pass will properly work.



Thanks to you Guy and Gal. Excellent!



Cheers Mates!



Jaime

R
Ronald Weaver 👤 Member for 23 years 3 months

Emma Seaton is correct. The dragging and dropping can also be done in the WBS view. This will move the WBS level plus all sub-level and their activties into the new (or established) project.

E
Emma Seaton 👤 Member for 20 years 9 months

Create a new programme file/stub (for want of better words!). Open both together and drag ’n’ drop the activities from the first programme into the second. Relationships will be maintained. If both need scheduling just open both together.

J
Jim Fairchild 👤 Member for 23 years 3 months

While you are in the Dates tab in the Project view also set the Must Finish By Date for the shorter project equal to the overall project completion date. This will allow Primavera to calculate the backward pass in inter-project links correctly.

It is a bit of a workaround but it works.

R
Rodel Marasigan 👤 Member for 19 years 7 months

Hi,



Yes it’s true but you can set the data date in the Project View before scheduling to have the same data date.



Cheers,

Rodel

S
Sudharsan V 👤 Member for 20 years 11 months

Hi,



The problem in P3e is, it will perform scheduling for first project as separate schedule and second one as separate schedule, eventhough u link the first one with second one.



It is accepted by Primavera and promised to perform as a single schedule in future

R
Rodel Marasigan 👤 Member for 19 years 7 months

Adre,



Yes you can do the same thing in P3e by creating two projects on one enterprise then open the enterprise and not just the project alone.



Regards,



Rodel

Forum Sponsor

Top Posters

Nick Johnson-Pond
3 posts
sairedz25
0 posts
Ahmed Awad
2 posts
Syed Shoeb
0 posts
Vimukthi
0 posts
bal aji
2 posts
Lee Mallek
23 posts
Viet Tran
9 posts
Ola Gbotoso
0 posts
Jaturapit Multongka
1 posts