Update actual labor units

W
Wasantha Nanayakkara 👤 Member for 22 years 8 months

Dinesh,



Same time check whether you selected any curve for the resource.

Then I think P5 is not allowing you to enter actuals in your settings. When you schedule, it will come to the same units what you had earlier.

Take the curve selection out.



Try this also and see.



Regards,



wasantha


W
Wasantha Nanayakkara 👤 Member for 22 years 8 months

Dinesh,



Then it should be correct.



I think the other thing you have to see is the ‘’ At completion unites’’ some times that will differ.

What I do is I open all under mentioned columns in Resource tab.



Budgeted units-Remaining units-Actual unites- At completion Units-unit percentage complete

Budgeted cost- Remaining Cost - Actual Cost



Before updating, make actual cost to Zero and see the units. Units should be same in the Budgeted, remaining and At completion. If not adjust it to budgeted units.

Then enter the Actual units (or units percentage complete)



Try this and see.



Regards,



wasantha


W
Wasantha Nanayakkara 👤 Member for 22 years 8 months

There are many settings in P5.

I am not sure the Types you select in the general tab for ‘’Duration Type’’ and ‘’Percentage Complete Type’’.





wasantha

Forum Sponsor

Top Posters

Nick Johnson-Pond
3 posts
sairedz25
0 posts
Ahmed Awad
2 posts
Syed Shoeb
0 posts
Vimukthi
0 posts
bal aji
2 posts
Lee Mallek
23 posts
Viet Tran
9 posts
Ola Gbotoso
0 posts
Jaturapit Multongka
1 posts