View, Layout, Save As then assign a layout name.
KB
Danovan,
Your query is not clear. I’m not sure if you are after on the resource curves that drive your resources profile or tracking module of P3 v5.
Resources curve are save global or default which enable you to select which curve are your going to use for each resources assigned on your activity task.
If you are after on tracking module you can save it available to all user or current user only on the tracking layout.
Hope this help.
Regards,
Rodel