Current progress against baseline?

A
Alex Wong 👤 Member for 23 years 4 months

Not sure this is what you ask for but you can use

"View"

"Progress Spotlight"



This will give you a progress line for with the data date line show whether the activity is ahead of behine schedule



HTH



Alex

A
Andrew Pearce 👤 Member for 25 years

I am struggling with same problem.

I can display bars for baseline OK

When I apply progress bars, progress is shown from actual start not baseline start?





In P3 %progress was shown from Target start date?

K
Kevin Button 👤 Member for 22 years 11 months

No offence taken. I’ve been using this software for a few years now and always find something else to learn and there’s sometimes half a dozen ways to do it.



Cheers

L
Lee Goulden 👤 Member for 21 years 6 months

Kevin, funny, now I read it again, your right, sorry no offence intended.

I just haven’t seen baseline progress done yet in P3e.

K
Kevin Button 👤 Member for 22 years 11 months

...define a new set of bars to reflect original baseline and report progress against these...



Which is what I was suggesting anyway, just said it a different way.

L
Lee Goulden 👤 Member for 21 years 6 months

There is no option to do this. Although it should be possible to define a new set of bars to reflect original baseline and report progress against these. It should be ...

K
Kevin Button 👤 Member for 22 years 11 months

Not sure that I fully understand what you need but you might need to play with some new bars and create one that uses the Plan Bar for the timescale and have the % Complete displayed on this bar.



KB

Forum Sponsor

Top Posters

Nick Johnson-Pond
3 posts
sairedz25
0 posts
Ahmed Awad
2 posts
Syed Shoeb
0 posts
Vimukthi
0 posts
bal aji
2 posts
Lee Mallek
23 posts
Viet Tran
9 posts
Ola Gbotoso
0 posts
Jaturapit Multongka
1 posts