Resource Calendar

A
Alex Wong 👤 Member for 23 years 4 months

Matthew



Is your activity type is Fix Unit/Time, if that is the case then you cannot change the Unit/time for the activity.



What I suggest is to change you activity type to fix duration (Be careful to check with your acitivity duration) change the resource UPT, change back the activity type to fix UPT.



This should do the job



HTH



Alex

Forum Sponsor

Top Posters

Nick Johnson-Pond
3 posts
sairedz25
0 posts
Ahmed Awad
2 posts
Syed Shoeb
0 posts
Vimukthi
0 posts
bal aji
2 posts
Lee Mallek
23 posts
Viet Tran
9 posts
Ola Gbotoso
0 posts
Jaturapit Multongka
1 posts