Problem of Date

A
Alex Wong 👤 Member for 23 years 4 months

My suggestion is pretty much the same, check the finish activity finish time. if it finish @ 00:59 is different from finish @ 17:59 where you successor will start next date.

Go Edit/User Preferece/Dates/Time/12hr or 24 hrs



HTH



Alex

M
MK TSE 👤 Member for 24 years 3 months

check the planning unit. If all in day, then check the working hour per day.



By default installation, it is 8hr per day. When do progress input by drag on bar instead of type in the value, the result may be fall into some decimal value and cause the problem

Forum Sponsor

Top Posters

Nick Johnson-Pond
3 posts
sairedz25
0 posts
Ahmed Awad
2 posts
Syed Shoeb
0 posts
Vimukthi
0 posts
bal aji
2 posts
Lee Mallek
23 posts
Viet Tran
9 posts
Ola Gbotoso
0 posts
Jaturapit Multongka
1 posts