Out of Sequence activities

M
Marcio Sampaio 👤 Member for 20 years 7 months

keep it simple ... "Or just read the schedule log and hunt those activties down"

R
Rashid Iqbal 👤 Member for 21 years 1 month

Kannan



You make a baseline, change the scheduling setting to ’progress override’ and then compare the finish date of the activties that are already started with the baseline dates. Populate a UDF saying "Out of Sequence" via global change and this will give you the ability to filter the activties.



Or just read the schedule log and hunt those activties down.



Regards

Rashid






M
Marcio Sampaio 👤 Member for 20 years 7 months

using your subject ...



what is the diference between out of sequnece activities and activities with unsatisfied relationships?



regards.

M
Marcio Sampaio 👤 Member for 20 years 7 months

Kannan,

Don’t think u can create a filter like this.

U have to schedule your project to see if there is any out of sequence activity.

Regards.

Forum Sponsor

Top Posters

Nick Johnson-Pond
3 posts
sairedz25
0 posts
Ahmed Awad
2 posts
Syed Shoeb
0 posts
Vimukthi
0 posts
bal aji
2 posts
Lee Mallek
23 posts
Viet Tran
9 posts
Ola Gbotoso
0 posts
Jaturapit Multongka
1 posts