WBS calendar

K
Kevin Button 👤 Member for 22 years 11 months

I think it’s a good idea, send email to primavera with this enhancement request and they will put it on the list.



Cheers

M
Marcio Sampaio 👤 Member for 20 years 7 months

I understand and i’m agree.



But I think that the ideal should be P5 to allows user to choose which calendar wbs consider.



Regards.

M
Marcio Sampaio 👤 Member for 20 years 7 months

I understand and i’m agree.



But I think that the ideal should be P5 to allows user to choose which calendar wbs consider.



Regards.

N
Niek Zonneveld 👤 Member for 21 years 3 months

Yep that’s the case.



I don’t see how it could work any other way, because how would you treat grouped activities with multiple calendars? (not just by WBS, but also any other (combined) grouping)



H.T.H.

N
Niek Zonneveld 👤 Member for 21 years 3 months

PRIM2849:



The original duration in the WBS summary bands is calculated as the following:



Latest Planned Finish - The Earliest Planned Start.



Project Manager uses the default Global calendar to determine the number of timeperiods based on the above calculation.



********************



This means that if your project calendar and the default global calendar are not the same, you can have deviations.



Hope this helps,



Niek.

Forum Sponsor

Top Posters

Nick Johnson-Pond
3 posts
sairedz25
0 posts
Ahmed Awad
2 posts
Syed Shoeb
0 posts
Vimukthi
0 posts
bal aji
2 posts
Lee Mallek
23 posts
Viet Tran
9 posts
Ola Gbotoso
0 posts
Jaturapit Multongka
1 posts