Bill, thanks - your suggestion worked! I couldnt find the Cost Units Linked until I went to Knowledgebase and found that it was because Id not got the column showing in the resource tab! Duh!! Now that I have all problems are solved and I shall have a very happy day - well better than Friday!!
1- You have to enter the units & prices in the resource directory (resource pool) , Units & Price Tape. Then assign this resource to its activity. By this way it will not reset to zero again. Because the Budgeted cost will be calculated by P3e according to the formula (BC = Price/Unit * Budgeted Unites) . If you obliged for any reason to change the Price/Unite in the recourse tape in the activity details , you have to do the following,
o Go to tools menu.
o Choose Recalculate assignment cost.
2- Do not change dates by dragging the activity. Depend on Schedule to do that.
Spider Project is most functional and powerful professional project management software.
The first SP version was launched in 1993 and since then it has been constantly improved. Today is used in 34 countries though most Spider Project customers are in Russia. Spider Project offers numerous unique functional features and is the only PM software that optimizes resource, cost, and material constrained schedules and budgets for projects and portfolios.
The unique features of Spider Project include Quantity Based Scheduling, Conditional Scheduling, Skill Scheduling, Optimal Resource, Cost and Material Leveling, Resource Critical Path Calculation, Cash and Material Flows Calculation and Management, Trend Analysis, Advanced Risk Simulation and Analysis, Calculation of Success Probability Trends, Calculation and Management of required Project Time and Cost Buffers, Application of Corporate Norms, Management of many Parallel Budgets, Multiple WBS and many others.
Spider Project was and is used for management of many large scale programs in Russia, including $51bln construction program for 2014 Winter Olympic Games preparation.
The application areas where Spider Project is successfully used include Aerospace, Banking, Construction, Defense, Energy, Engineering, Infrastructure, Manufacturing, Metallurgy, Mining, Oil & Gas, Railways, Retail, Shipbuilding, Software Development, Telecommunications, Utilities, etc.
P6-Auditor - Display information from Primavera P6 audit tables in a user-friendly format
Unifier-Archiver - Extract and archive important documents and attachments from Primavera Unifier
Unifier-Loader - Load data into and out of Unifier via Excel
PCM-Loader - Import data into Primavera Contract Management with flexible and secure, template-driven Excel spreadsheets
PCM-Archiver - Extract and archive important documents and attachments from Primavera Contract Management
PCM-Unifier Migrator - Automatically transfer live and historical data from Primavera Contract Management to Primavera Unifier with ease
Create Radically Better Construction Schedules with ALICE Technologies
Use the power of AI to create construction schedules that reduce risk while cutting costs and build time. With ALICE, develop the ideal schedule during preconstruction -- or recover projects that are off schedule and over budget.
Thanks for your replies guys.
Bill, thanks - your suggestion worked! I couldnt find the Cost Units Linked until I went to Knowledgebase and found that it was because Id not got the column showing in the resource tab! Duh!! Now that I have all problems are solved and I shall have a very happy day - well better than Friday!!
Cheers
Emma
Emma
You may avoid that by two ways,
1- You have to enter the units & prices in the resource directory (resource pool) , Units & Price Tape. Then assign this resource to its activity. By this way it will not reset to zero again. Because the Budgeted cost will be calculated by P3e according to the formula (BC = Price/Unit * Budgeted Unites) . If you obliged for any reason to change the Price/Unite in the recourse tape in the activity details , you have to do the following,
o Go to tools menu.
o Choose Recalculate assignment cost.
2- Do not change dates by dragging the activity. Depend on Schedule to do that.
Please give me the feedback.
Regards
If you are not tracking units, you can uncheck "cost units linked". This is set for each assignment in the resources tab.
Regards,
Bill