Compare progress

M
Marcio Sampaio 👤 Member for 20 years 7 months

Amar,



I understand that Bl activity % Complete is how much activity must have progressed - until the actual data-date - based on baseline.



If it’s correct, i can use it like a planned progress and compare with "Activity % Complete".



Tell me if u agree.



Regards.



Marcio Eduardo

A
Amar Aghana 👤 Member for 20 years 10 months

Marcio, there is one more thing to understand. That is Performance % Complete. Please try and understand. I have some tips. But I am experimenting. Let me share with you once I am sure. Thanks, Amar.

A
Amar Aghana 👤 Member for 20 years 10 months

Marcio,



I too had same problem. When you change Activity % Complete, based % Completion type (Physical / Duration / Units), the appropriate % will be considered.





For eg, if an activity % Completion type is Physical when you enter Activity % Complete as 5%, Physical % = 5%,





But I am not able to understand how you have % Complete in Baseline.



Regards, Amar.

Forum Sponsor

Top Posters

sairedz25
0 posts
Ahmed Awad
2 posts
Syed Shoeb
0 posts
Vimukthi
0 posts
bal aji
2 posts
Lee Mallek
23 posts
Viet Tran
9 posts
Ola Gbotoso
0 posts
Jaturapit Multongka
1 posts
James Williams
74 posts