Primary baselines

G
Gordon Blair 👤 Member for 20 years 10 months

If this phenomenon only occurs where progress is reported on an activity, then ’%complete NE 0’ should give you a reasonable stab at the filter for a Global Change.

Cheers,

Gordon

A
Alex Wong 👤 Member for 23 years 4 months

Keith



I know that you can use that expression of



{Plan Start = Early Start}



In the global change expression



What you need to do is use a activity code to filter the activity you would like to change and then run the above expression.



It should work



Cheers



ALex

K
Keith Fisher 👤 Member for 20 years 8 months

Changing the primary dates works for me in this instance thanks, just wish i could do a global change rather than change the values manually.



ie where... planned start...does not equal....."no option available" but at least i have a solution thanks again.

S
Steven Oliver 👤 Member for 23 years 7 months

The "baseline" uses the fields "planned start" and "planned finish" fields, as opposed early start/early finish most people are use to.



For completed and future activities, these dates are correctly set to early start/early finish, but for activities in progress, these fields are set from the first time that scheduling took place.



Check that the "planned start" and "planned finish" dates are reflective of the baseline you want to create. Adjust if necessary and re-baseline.





HTH

Forum Sponsor

Top Posters

sairedz25
0 posts
Ahmed Awad
2 posts
Syed Shoeb
0 posts
Vimukthi
0 posts
bal aji
2 posts
Lee Mallek
23 posts
Viet Tran
9 posts
Ola Gbotoso
0 posts
Jaturapit Multongka
1 posts
James Williams
74 posts