It is really a very important function and i used it in my efforts to level the reosurces manually. Anyways, as now i know it is not there, i ll try to find some other method. Thanks a lot.
Im afraid this one is still missing in P3e Rashid.
The best way to go about this is to call Primavera and add you name/company to an enhancement request. If more users are missing this functionality there is a distinct chance it will be incorporated in one of the next releases.
P3e/c or P3e is only 50% powerful on reports and in handling resource & cost account.Even it has flaw on organzing resource & cost account if you have multiple assignment on one activity.
Getting back to peak,it does not have this option.The only available is average on spread sheet option.
this is the same for resource profile.The profile do not have any flexibilty in changing y axis.It does not show data values on top of resource profile also as in p3 graphics.
Spider Project is most functional and powerful professional project management software.
The first SP version was launched in 1993 and since then it has been constantly improved. Today is used in 34 countries though most Spider Project customers are in Russia. Spider Project offers numerous unique functional features and is the only PM software that optimizes resource, cost, and material constrained schedules and budgets for projects and portfolios.
The unique features of Spider Project include Quantity Based Scheduling, Conditional Scheduling, Skill Scheduling, Optimal Resource, Cost and Material Leveling, Resource Critical Path Calculation, Cash and Material Flows Calculation and Management, Trend Analysis, Advanced Risk Simulation and Analysis, Calculation of Success Probability Trends, Calculation and Management of required Project Time and Cost Buffers, Application of Corporate Norms, Management of many Parallel Budgets, Multiple WBS and many others.
Spider Project was and is used for management of many large scale programs in Russia, including $51bln construction program for 2014 Winter Olympic Games preparation.
The application areas where Spider Project is successfully used include Aerospace, Banking, Construction, Defense, Energy, Engineering, Infrastructure, Manufacturing, Metallurgy, Mining, Oil & Gas, Railways, Retail, Shipbuilding, Software Development, Telecommunications, Utilities, etc.
P6-Auditor - Display information from Primavera P6 audit tables in a user-friendly format
Unifier-Archiver - Extract and archive important documents and attachments from Primavera Unifier
Unifier-Loader - Load data into and out of Unifier via Excel
PCM-Loader - Import data into Primavera Contract Management with flexible and secure, template-driven Excel spreadsheets
PCM-Archiver - Extract and archive important documents and attachments from Primavera Contract Management
PCM-Unifier Migrator - Automatically transfer live and historical data from Primavera Contract Management to Primavera Unifier with ease
Create Radically Better Construction Schedules with ALICE Technologies
Use the power of AI to create construction schedules that reduce risk while cutting costs and build time. With ALICE, develop the ideal schedule during preconstruction -- or recover projects that are off schedule and over budget.
It is really a very important function and i used it in my efforts to level the reosurces manually. Anyways, as now i know it is not there, i ll try to find some other method. Thanks a lot.
Regards
Rashid
Im afraid this one is still missing in P3e Rashid.
The best way to go about this is to call Primavera and add you name/company to an enhancement request. If more users are missing this functionality there is a distinct chance it will be incorporated in one of the next releases.
Cheers,
Niek.
P3e/c or P3e is only 50% powerful on reports and in handling resource & cost account.Even it has flaw on organzing resource & cost account if you have multiple assignment on one activity.
Getting back to peak,it does not have this option.The only available is average on spread sheet option.
this is the same for resource profile.The profile do not have any flexibilty in changing y axis.It does not show data values on top of resource profile also as in p3 graphics.