Add Resource Via Global Change
Forum Sponsor
Top Posters
sairedz25
0 posts
Ahmed Awad
2 posts
Syed Shoeb
0 posts
Vimukthi
0 posts
bal aji
2 posts
Lee Mallek
23 posts
Viet Tran
9 posts
Ola Gbotoso
0 posts
Jaturapit Multongka
1 posts
James Williams
74 posts
hi guys
why not u go to SQL and have Liberty to PLay with Primavera file
this the most quickest way to deal with P3 data
Good one, it helped.
Regards
Rashid
You cannot do this through global change, but you can quickly assign multiple resources at once using assign resource dialog. Use filter to highlight the activities that meet your criteria. Not the same thing, but perhaps this will help.
Regards,
Bill