Add Resource Via Global Change

M
MUHAMMAD IQBAL 👤 Member for 20 years 9 months

hi guys



why not u go to SQL and have Liberty to PLay with Primavera file



this the most quickest way to deal with P3 data


B
Bill McMichael 👤 Member for 21 years 6 months

You cannot do this through global change, but you can quickly assign multiple resources at once using assign resource dialog. Use filter to highlight the activities that meet your criteria. Not the same thing, but perhaps this will help.



Regards,

Bill