Invalid Relationships & Not ideal critical path!
Forum Sponsor
Top Posters
Nick Johnson-Pond
3 posts
sairedz25
0 posts
Ahmed Awad
2 posts
Syed Shoeb
0 posts
Vimukthi
0 posts
bal aji
2 posts
Lee Mallek
23 posts
Viet Tran
9 posts
Ola Gbotoso
0 posts
Jaturapit Multongka
1 posts
Change your bar view to show float as well. You have some activities with no successor or long float which changes the critical path.
Thanks for the reply!
All the invalid relationships has an Finish milestone actvity type because it is all completion works.
I need to determine the logical and real critical path but the result is very far from reality.
try using finish milestones and FF links (for invalid relationships)
for expected critical path - try to use FS links (only!)