Cost / Budget Transfer

N
Neal Walsh 👤 Member for 18 years 9 months
N
Neal Walsh 👤 Member for 18 years 9 months

Kevin,



Thanks for the reply, but that isn’t quite what I meant. I know how to modify costs / resource rates and alter the budget, that’s not the issue, I wanted to know exactly how to take money out of one activity (that has completed at a lesser cost) and transfer to another. For example, I have a job that costs £100, and takes a couple of days to complete. The task actually only costs £80, so I don’t want to schedule it showing the At Completion to be £100, I want to show it as £80 then I can use the saving of £20 on another activity. If I have resources assigned to the said activity that I know havent booked any time to the Activity Code, I can simply remove them and re-assign to another Activity. I wanted to know if there was a better method for re-distribruting unused costs. The client thinks the Activity costs £100 as it was signed off as that in the Baseline Programme / Target Price, so I might as well keep the £20 and use for an Activity that may need it!



Walshy

K
Kevin Ton 👤 Member for 19 years 7 months

There are two ways to assign / change cost to activities:

1. you can change the cost rate for resource which you assigned to activity to change the total cost

2. or you can directly assign cost to the activity cost budget under resource tab.



so, what you can do is to assign cost rate to first activity make the budget equal to 9716.7 and then assign the cost rate for LOE activity to make the cost budget = 8399.96.



Hope that help your question.

Forum Sponsor

Top Posters

Nick Johnson-Pond
3 posts
sairedz25
0 posts
Ahmed Awad
2 posts
Syed Shoeb
0 posts
Vimukthi
0 posts
bal aji
2 posts
Lee Mallek
23 posts
Viet Tran
9 posts
Ola Gbotoso
0 posts
Jaturapit Multongka
1 posts