Copying a Project

Hi Guys!

Some help please...

I have no idea why I can't copy a project in my P3. The error always says "Invalid Project Name". No project Group and Project name is 4 characters. So, what i used to do is to copy the folder containing the project and rename it just to copy the project.

Any sort of advice & solutions...

 

Thanks,

 

Ariel

R
Ronald Winter 👤 Member for 23 years 5 months

Ariel,

 

You need to put the new name of the schedule in the Project Group field and leave the Project Name field empty.  Project Name is for when you have subprojects under the Project Group name.  Good luck!