Hi Planners,
I have trasfered data from SAP to P3 then p3 to p6. I got everything except following:
The budgeted hours and original durations are not same. In p3 valueas are same as SAP but not in P6. I think both values are 8 times more. It may cause of some setting or its the way. Can you please resolve my issue as soon as you can. Otherwise I will have to re assign manualy. There are more then 7000 activities.
Thanks
Minhas
Hello Minhas,
in P3 you can only have one duration unit for a project; in P6 you may use several duration and work units in a specific project
a ratio of 1 to 8 makes me think that the unit is Day in P3 and Hour in P6
if so, you should divide the duration by 8 in P6 by using Global Change
Alexandre