P3 TO P6 Units issue

Hi Planners,

I have trasfered data from SAP to P3 then p3 to p6. I got everything except following:

The budgeted hours and original durations are not same. In p3 valueas are same as SAP but not in P6. I think both values are 8 times more. It may cause of some setting or its the way. Can you please resolve my issue as soon as you can. Otherwise I will have to re assign manualy. There are more then 7000 activities.

Thanks

Minhas

A
Alexandre Faulx-Briole 👤 Member for 23 years 4 months

Hello Minhas,

in P3 you can only have one duration unit for a project; in P6 you may use several duration and work units in a specific project

a ratio of 1 to 8 makes me think that the unit is Day in P3 and Hour in P6

if so, you should divide the duration by 8 in P6 by using Global Change

Alexandre

Forum Sponsor

Top Posters

Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts
Simon Gumede
0 posts