UPDATE PROGRESS MANUALLY

V
vex zex 👤 Member for 15 years 11 months
R
Rodel Marasigan 👤 Member for 19 years 7 months

Vex,

Update % complete and enter remaining duration. Do the same on resources if assigned. Very simple.

V
vex zex 👤 Member for 15 years 11 months

hye anoon



thanks for the suggestion..

how to update the progress each activity if not based on duration and just based on pysical percentage

A
Anoon Iimos 👤 Member for 19 years 8 months

Vex,



That is not possible if your activities are not progressing as planned. However, it maybe done by reducing some durations for your activities, or why not use your baseline or target (progressed as planned)?