Hi Mike
The way you run the schedule is quite incorrect
You use actual dates to the activities but the data date is not scheduled accordingly
Data date is the start date to run the scheduling algorithm
Mike,
The problem is the predecessor because it was progress 100 percent complete sitting after the data date therfore the successor will run on the data date.
Note: All actual progress activities specially completed should sit after the data date and remaining will run after the data date.
Data Date mean Status date (cut-off of actual completed activities).