P3 changing dates

M
Mike Miller 👤 Member for 16 years 1 month
S
Shah. HB 👤 Member for 17 years 6 months

Hi Mike



The way you run the schedule is quite incorrect



You use actual dates to the activities but the data date is not scheduled accordingly



Data date is the start date to run the scheduling algorithm

R
Rodel Marasigan 👤 Member for 19 years 7 months

Mike,

The problem is the predecessor because it was progress 100 percent complete sitting after the data date therfore the successor will run on the data date.



Note: All actual progress activities specially completed should sit after the data date and remaining will run after the data date.

Data Date mean Status date (cut-off of actual completed activities).

Forum Sponsor

Top Posters

Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts
Simon Gumede
0 posts