Combine 2 Revision is it possible?
Forum Sponsor
Top Posters
Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts
Simon Gumede
0 posts
Go to gantt chart area, right click -> select Bars (OR use Ctrl F11) and then under defined bars section, u can define current and target bars.
Select the position 1/2
:-)
Kumar
I have thought about that i think this is the only way but is is possible to have two summary bars reflecting the current and target?
thanks
Hi Pacifico,
Make Target2 of revision 2 as the 2nd target file of Revision 1.The current file should be the same for both revisions.
Now you have one file with target 1 & 2 and the current file.
Does this solve your problem?
Regards,
Santhosh