Unable to edit Baseline

G
Gary Whitehead 👤 Member for 17 years 2 months

Moved to P3 forum.



Raj: The software is supposed to move any activities that have not yet started to the data date when you press F9. The theory is, if it hasn’t started yet, it shouldn’t be showing in the past.

To tell the software an activity has started, check the ’actual’ box when you enter the start date.



If you want to change the baseline mid project, open up the target project whilst you do not have your live project open, you should be able to make the changes as normal.

R
Rangarajan Ramaswamy 👤 Member for 16 years 6 months

thanx a lot yakub, i know that , but what if i have to change the baseline in the middle of the project.and also i have checked the activities but i dont know the first activity of every new project m creating automatically sets to the current start date and even if i change it to some back date , after pressing F9 it automatically shifts to the current schedule data in the F9 option

S
shaik yakub 👤 Member for 18 years 10 months

Raj,

You can edit the Target dates only in the Baseline Programme But not in the Updated Schedule where u have assigmned target. Regarding the dates check the links of the activities.





Shaik

Forum Sponsor

Top Posters

Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts
Simon Gumede
0 posts