Scheduling issue

S
Shah. HB 👤 Member for 17 years 6 months
A
Alexandre Faulx-Briole 👤 Member for 23 years 4 months

Shahul,

the result depends on:

a) the activity type: Task = Duration and activity calendar, Independant = Duration and assigned resources calendars, Meeting = Duration and workperiods where all the assigned resources are working at the same time

b) is the resource driving or not? Driving = Resource, not driving = Duration

I hope it helps,

Alexandre