Resource histogram for tender projects

S
Shah. HB 👤 Member for 17 years 6 months
S
Shah. HB 👤 Member for 17 years 6 months

Thanks Mr.Mike and Mr.Samer for the detailed explanation

M
Mike Testro 👤 Member for 20 years 5 months

Hi Se



That is my point entirely.



Except that if you are going to use a broad percentage the plus / minus averages will even out.



This is going against my usual concept of lots of little guesses is better than one big one.



But anyway I am losing interest in this topic.



Best regards



Mike Testro

S
Se de Leon 👤 Member for 25 years

Hi Shahul,



The devil is always in the details. The less details you use in the resource histogramme, the less accurate it will be unless you have the experience doing the same project.



Just my 2 cents.

M
Mike Testro 👤 Member for 20 years 5 months

Hi Shahul



You wrote



Mr.Mike would u please explain about resource hours and working hours as u mentioned in previous message



it is simple arithmetic- as samer said the total cost of any project or section threrof consist of money totals for:



1. OH&P

2. Materials

3. Plant

4. Labour



Each has its own % content.



Once you have taken out the OH&P you have the net contract value.



Then you apply a reasonable labour % that represents the labour value.



This gives you the labour resource cost - in money.



Divide this by the appropriate labour rate and you have the resource hours in the contract sum.



This is the starting point for resource modelling in your software.



Sometimes I wonder why I bother.



Best regards



Mike Testro

S
Samer Zawaydeh 👤 Member for 17 years 10 months

Dear Mike,



In addition to the reduction of the OH&P, usually, a percentage for "Management Reserve" exists. This should be reduced as well from the Budget at completion amounts.



Dear Shahul,

The basic idea is to know that you have different categories of resources (Material, Equipment and Manpower) and each month you will have a different distribution.



With kind regards,



Samer

S
Shah. HB 👤 Member for 17 years 6 months

Mr.Mike would u please explain about resource hours and working hours as u mentioned in previous message

M
Mike Testro 👤 Member for 20 years 5 months

Hi Sahul



Not using P3 but a spreadsheet.



For a very broad - global - resource allocation take the contract sum - reduce it by the OH&P percentage to get the net figure.



Apply an estimated figure for the labour content - depending on the project somewhere between 25% and 35%.



This will give the labour value - divide this by the average hourly labour rate and you will get an estimated labour hours total in the project.



This number of hours can be applied to the top summary bar at level 1 in P3.



To get an average gang size divide the hours by the number of work hours available in the project.



For a more detailed application set down the work hours available in each activity and apply the resource hours pro rata to each activity - the gang size will be the ratio of resource hours to work time hours.



Best regards



Mike Testro.

Forum Sponsor

Top Posters

Josephus Enot
1 posts
Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts