Adding more activities to base line schedule

W
Waseem Saber 👤 Member for 21 years 6 months

Agree with Gary,



it is imperative that you rebaseline by including this new scope and this should be submitted for acceptance and then this will become your new baseline.



wondering what are the conditions of the contract...?



cheers



Waseem Saber

G
Gary Whitehead 👤 Member for 17 years 2 months

1) Copy ther approved baseline schedule,

2) update WBS, activitites, resources, schedule, logic, etc to reflect additional works

3) Make sure you understand & can defend any impact on the schedule for original scope arrising from the addition of the new works.

4) Issue new baseline schedule, manpower loading, cashflow forecasts, etc for approval

Forum Sponsor

Top Posters

Josephus Enot
1 posts
Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts