how to shedule activities based on resourses

E
elnur ganbarov 👤 Member for 17 years 3 months

Dear Kafo



thanks for help specialy for that part



Now for scheduling : you can either schedule based on resourecs availability or you can even stretch your project and Do a resource leveling to avoid "Resource Histogram Spikes" - i.e. sudden increases / decreases in the budgeted amounts)

K
kafo souq 👤 Member for 17 years 3 months

Dear



Simply set the resourecs as driving



(Driving resources are those that control the duration of the activity only based on their availability Max / Min)



In P3 this is a small tick box at the resources dialog box , just tick driving and there you go



Now for scheduling : you can either schedule based on resourecs availability or you can even stretch your project and Do a resource leveling to avoid "Resource Histogram Spikes" - i.e. sudden increases / decreases in the budgeted amounts)



If your resource is money - Selling Price / Revenue Etc- Make sure not to assign any value to the resource until you finish scheduling and you are satisfied with the results and then load you values



Hope this answered you question

Forum Sponsor

Top Posters

Josephus Enot
1 posts
Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts