Monte Carlo

O
Omar Grant 👤 Member for 20 years 8 months

Hi Barry, I still think my first suggestion is the best but obviously requires Pertmaster or some similar product which will produce the schedule completion probablity curve for each schedule which can be compared in a table etc. If your front-end activities in the current schedule truly have increased the schedule risk then Pertmaster should (at least in theory!!) highlight those activities as high in cruciality etc. Otherwise, (and I assume both schedules are resource loaded?) dropping the resource loads into Excel for both schedules and comparing the front end loadings? Hope this helps

B
Barry Fullarton 👤 Member for 17 years 5 months

Hi Omar



what I am trying to achieve is the following



1. I have a baseline program as submitted buy the Contractor. This I am using in P3 as my Target or Baseline

2. I then have my current schedule and to this has been added activities , or scope of work , but shows the same completion date

3. What I need to demonstrate in a Curve is the Front end load of the additional scope and showing that this additional Scope has added or increased the risk of the Projects Completion Date



Regards

O
Omar Grant 👤 Member for 20 years 8 months

Hi Barry - do you have Pertmaster or a similar program? If you do you could run the risk analysis on each of your schedules to get the probablity values 0-100% for each then graph into Excel - is that what you are after?



cheers,



Omar

Forum Sponsor

Top Posters

Josephus Enot
1 posts
Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts