P3 programme transfering

A
Ahmed Khan 👤 Member for 17 years 6 months
K
KK KEYAN 👤 Member for 17 years 7 months

Dear Maask,



Don’t worry. All new activities if anything is there will be added while importing. Better export the activity description also. so that you it can be imported. otherwise Description will be blank.



Hope I’ve cleared your doubt.



Thank you.



Regards,

R.K.KARTHIKEYAN.

A
Ahmed Khan 👤 Member for 17 years 6 months

Kartikeyan,



Let me tell U the actual,



U understood my problem I have added the few new activities in the new plan. So how to do that.



Regards



Maask

K
KK KEYAN 👤 Member for 17 years 7 months

Dear Maask Kharadi,



I am not getting you properly. If you want to transfer the updation, then follow as mentioned below.



If you have the same activity id in both the program, then you can export the updated program with the details viz., Activity id,Actual dates & percentage complete, then import it in the program in which you need the update.



Hope this will do.



Thank you.



Regards,

R.K.KARTHIKEYAN.

Forum Sponsor

Top Posters

Josephus Enot
1 posts
Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts