Plz follow the P3 Tutorials.
Hope this will help. Or else come back to me.
Regards
Maask
Dear Anu,
Please follow the link below. I guess the procedure that I have stated therein is the answer to your question.
http://www.planningplanet.com/forum/forum_post.asp?fid=1&Cat=1&Top=53861
In Service,
Ferdinand
Hello Tommy Nug,
If my client want to see the driving relation of a activity in 3 level of predecessors and successors in barchart format.
How am I prepare one?, please recommend.
Otherwise, you can check the asterisk mark at the middle column between Activity ID and Relationship type.
Cheers,
Tom
Hi Anu,
Driving logice will have FF=0. You can base on that concept to define the driving activities.
Cheers,
Tom