Importing % Progress from Old Schedule to New Schedule

B
Brennan Westworth 👤 Member for 23 years 3 months

two ways i can think of are to use export import or target update



export import



1. back up both schedules



2. open the old schedule and to go tools, project utilities, export



3. add a new specification



4. in the content tab include only activity ID and % complete (you might also want remaining duration)



5. in the format tab I usually use .DBF you can keep the file name C:\P3WIN\P3OUT\P3 if its just a 1 off.



6. leave selection blank for all activities or set up a filter for the activities you want and click RUN



7. open the new schedule



8. go to tools, project utilities, import



9. add a new specification



10. enter the path to your file (C:\P3WIN\P3OUT\P3.DBF)



11. cross your fingers and click RUN





or u could use Target update



1. back up both schedules



2. Open the old schedule



3. go to tools, project utilities, targets and set the new schedule as a target.



4. select the new schedule and click the update button. You may need to try this a couple of times with different options selected in the update target dialogue box







HTH

Forum Sponsor

Top Posters

sairedz25
0 posts
Ahmed Awad
2 posts
Syed Shoeb
0 posts
Vimukthi
0 posts
bal aji
2 posts
Lee Mallek
23 posts
Viet Tran
9 posts
Ola Gbotoso
0 posts
Jaturapit Multongka
1 posts
James Williams
74 posts