Early Start vs. Actual Start in P3.1

R
Ruel Camaquin 👤 Member for 17 years 6 months

It is a very big help! i’ve even added variance column, now i can see me delays and ahead in my schedule.



Thank you so much.

R
Ruel Camaquin 👤 Member for 17 years 6 months

I aleady have a target schedule. The only thing is that everytime i encode the actual start and finish dates, the early start column dates also changes to the actual dates i encoded. Ex. masonry works early start is 10NOV08 as the target, then i encoded 15NOV08 as an actual start for masonry works - after i clicked the ok button, the early start date for the target also changes to the actual start date of 15NOV08A although the bar chart does not move.



I cannot compare the early start and the actual start with just the bar charts alone, i need to have the early start dates same as the target reference against the actual start.

Forum Sponsor

Top Posters

sairedz25
0 posts
Ahmed Awad
2 posts
Syed Shoeb
0 posts
Vimukthi
0 posts
bal aji
2 posts
Lee Mallek
23 posts
Viet Tran
9 posts
Ola Gbotoso
0 posts
Jaturapit Multongka
1 posts
James Williams
74 posts