Project Had 1 day for install after long lead, then 1 day install, then Substantial Completion. But in fact the install and detail such as testing would take 30 days. The long lead is taking longer - they want more for "supply chain" disruptions (aren't thos over) - isn't all the delay on the contractor for under-estimating delivery, not getting procured in time, and the bad logic and or not enough duration. All on contractor to make up or get LD's?
How accountable can Contractors be held for scheduling errors? For example...