Monitoring of SPI in a Project

K
Kannan CP 👤 Member for 18 years

At what stage in a Project, the monitoring of SPI should be stopped,

1. is it after the baseline program completion date is over, but still with works ongoing in delay. 

2. or earlier, noticing that project is in significant delay and will not meet target.

Regards

Kannan

P
Peter Holroyd 👤 Member for 21 years 1 month

When it is easier to do a resourced contract close out list (inc snagging). Use JIRA (or similar) and burn down those actions!

Profile picture for Patrick Weaver
Patrick Weaver 👤 Member for 25 years 5 months

Traditional SPI becomes increasingly unreliable after the mid point of the project - certainly in the last third as it trends back towards 1.0.  It is also a relatively meaningless number all changes in SPI can tell you is there has been as change in the values used to calculate the ratio.  

If you are looking for a realistic projection of completion based on Earned Value Management (EVM) data, consider using Earned Schedule (ES) the concept has been around for nearl 20 years now and the tools are free to access and use. All you need to to transpose your EVM data into the calculator. 

For more on ES see: https://mosaicprojects.com.au/PMKI-SCH-040.php#Process2

Forum Sponsor

Top Posters

Adrian Fletcher
12 posts
GeoVe
0 posts
James Williams
74 posts
Abkar Bannayan
25 posts
christiandt
0 posts
J Vaartjes
3 posts
Aidar Kurmantayev
0 posts
Noe Radovan
8 posts
Johannes Vandenberg
14 posts
Soheil Barekat
4 posts