Planned values of Early & Late curves Vs Actual value

K
Kannan CP 👤 Member for 18 years

Interpretation of Progress S-Curve without Schedule

Case-1  the actual overall actual progress value of reporting period is less than the overall early planned value but above the overall late planned  value:  the agreed baseline completion of Project may or may not get extended, all depends on the progress achieved on the planned critical path.

Case-2  the overall actual value reported is below the overall late planned  value:  does it mean that the agreed Project completion date is extended, or it depends on the progress on the critical path

Appreciate your kind thoughts....

Kannan

Profile picture for Patrick Weaver
Patrick Weaver 👤 Member for 25 years 5 months

The volume of work completed is a good indication of progress overall but you need to be using something like Earned Duration or Earned Schedule to see the potential effect. These techniques forecast completion based on performance to date and have been shown to be reliable indicators, see: https://mosaicprojects.com.au/PMKI-SCH-040.php#Process2  

However, this is different to the measure of progress on the critical path. You need both for a complete picture, but you also need to recognise the projected completion based on CPM is wildly optimisitic: https://mosaicprojects.com.au/PDF_Papers/P117_Why_Critical_Path_Scheduling_is_Wildly_Optimistic.pdf

Forum Sponsor

Top Posters

Adrian Fletcher
12 posts
GeoVe
0 posts
James Williams
74 posts
Abkar Bannayan
25 posts
christiandt
0 posts
J Vaartjes
3 posts
Aidar Kurmantayev
0 posts
Noe Radovan
8 posts
Johannes Vandenberg
14 posts
Soheil Barekat
4 posts