Is there a "time" reference for schedules? Gordian RS Means = Cost? ie, install 10k steel (of SF) for bldg
Would it be useful? Sometimes it is not the project or schedule that is late, it is a bad completion duration based on conventional construction practices (yes, a contractor should see that - but most will take a (too) short (aggressive schedule) job knowing they can extend it one way or the other. I have worked for enough contractors to know they do not overly analyze that aspect in fact - I often see a too high bid that incorporated the schedule vs the winning bid which was the contractor who knew they could push "delays" to construct without the extra cost (such as extended hours, weekends, mult. crews, etc.)
Is there a "time" reference for schedules? Gordian RS Means = Cost? ie, install 10k steel (of SF) for bldg
Forum Sponsor
Top Posters
Adrian Fletcher
12 posts
GeoVe
0 posts
James Williams
74 posts
Abkar Bannayan
25 posts
christiandt
0 posts
J Vaartjes
3 posts
Aidar Kurmantayev
0 posts
Noe Radovan
8 posts
Johannes Vandenberg
14 posts
Soheil Barekat
4 posts