Hello,
I have done a test updating the schedule at a specific data date (last week):
1- Updating without correcting the out of sequence activities----> result: 32 days of delay
2- Updating with correcting the out of sequence -----> result: 10 days of delay.
Question: Do I have the right to make the correction of out of sequence to meet the actual scenario on the site in order to give an accurate data or I should not make any changes in the current schedule.??
You have the right to make the correction of out of sequence work.
The update should reflect real world conditions.
Also in your update narrative I would state what I did and why I did it
If you did not correct it your would be over inflating your dealy.
From an owners perspectivie he gladly embrace the shorter delay.