BASELINE DATES

Gents, I need your help.

I noticed that some of the activities in my schedule displays baseline dates that are not corresponding to their dates in the baseline schedule.

 Not all the activities, just some few. 

How you I solve this issue?

Thanks for your help.

Z
Zoltan Palffy 👤 Member for 16 years 10 months

NO if you have not maintained or assigned a baseline then how in the world can you expect information from that schedule  ?

P
Prosper Kalabar 👤 Member for 8 years 1 month

Thanks Gareth. 

Have checked. the early stat and early finish both align with the start and finish dates respectively

G
Gareth Jones 👤 Member for 6 years 3 months

Hi On your baseline check that the your planned dates and Early dates align.

Gareth

P
Prosper Kalabar 👤 Member for 8 years 1 month

Thanks for your response. 

haven't maintained/ asigned BL yet.

But then since I haven't, the current schedule start & finsh dates should display as the baseline start/ finish dates as well. But some activities (not all) are displaying dates displaying BL dates different from the schedule date.

Am using BL Project Start & BL Project Finish to display the information

Z
Zoltan Palffy 👤 Member for 16 years 10 months

have you sleected maintain baseline ?

have you selected assign basline ?

what columns are you using to display the baseline dates ?

what is your earned value calculation set to ?

Forum Sponsor

Top Posters

Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts
Simon Gumede
0 posts