EV and PV using cost and hours

Hello,

I noticed that primavera P6, calculate EV and PV only from cost value, what if we want to calculate EV and PV from labour units.

Imagine if we have ressource loaded a schedule with hours and cost, how can we obtain the EV and PV in different point of views cost and hours separetely

A
Abderrahim OUBDI 👤 Member for 6 years 4 months

Primavera can calculate EV and PV only for each activitiy if it is loaded in hours (labor units) but he cannot give the EV or PV in the WBS summary of the activities unless you assign the PRICE/UNIT equals to 1.

Z
Zoltan Palffy 👤 Member for 16 years 10 months

Just go to columns and add a column it is under earned value its called Earned Value Labor Units

Forum Sponsor

Top Posters

Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts
Simon Gumede
0 posts