Problem with importing resources in P6

P
Prince Raju 👤 Member for 6 years 10 months

Good day!

 

I have a small query...please help me to resolve it if you can

When I’m importing a project in P6, resources(budgeted labour units) are not showing the same value as per the imported project.

Awaiting your replies

 

Thanks in advance 

 

Prince Raju

Z
Zoltan Palffy 👤 Member for 16 years 10 months

make sure that durgin the import process thet you select modify then for the resource select insert new

Z
Zoltan Palffy 👤 Member for 16 years 10 months

make sure that calculate cost from units is NOT checked. Also at the project level under the resource tab make sure that Resources can be assigned to the same activity more than once is NOT checked

Forum Sponsor

Top Posters

Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts
Simon Gumede
0 posts